(NewsDakota.com) – Work on the final phase of the Business Loop East construction project in Jamestown resumed this week.
Phase 3 of the project began this week. Phase 3 involves reconstruction of 14th Street Southeast (the frontage road) from 16th Avenue Southeast to 13th Avenue Southeast.
Project manager Patrick Hockett with Sellin Brothers Inc., says the Business Loop East project is scheduled to be completed June 2. Previous phases of the project were completed last summer and fall.
Business Loop East will remain open during most of the Phase 3 construction this spring.