VALLEY CITY, N.D. (NewsDakota.com) – 3rd St NE from Central Ave to 3rd Ave NE and 3rd Ave NE from 2nd St NE to 3rd St NE is closed. The intersection of 2nd Ave NE will remain open at all times during the construction of Phase 2. The closure will remain in effect until the corridor is reconstructed, which is anticipated to be late July. No detour route for motorized vehicles will be provided, temporary pedestrian access routes will be provided along the project route for the duration of the project.

Beginning Monday, June 10, 2024, the intersection of 3rd Ave NE and 2nd St NE will be closed for utility work. This closure is anticipated to be in effect until Friday, June 14, 2024.

Updated maps for all road closures will be posted on the City of Valley City’s webpage https://www.valleycity.us/engineers when they are taking affect. If you have any questions regarding the project, please contact KLJ at (701)-845-4980.