VALLEY CITY, N.D. (NewsDakota.com) – Here is the latest update on road reconstruction in Valley City from KLJ project engineer Chad Pedersen.

Streetscape Phase II (Central and Main Street)

All concrete sidewalks and ADA ramps will be complete the middle of this week. Milling of existing pavement along Central Avenue is scheduled for Friday of this week. Asphalt overlay is scheduled for the end of next week (Week Ending 10/9), Street light and traffic signal installation should be complete late this week or early next week.

7th Ave NW/4th St NW

Concrete sidewalks and driveways are being placed this week, September 27 – October 1. Asphalt Paving the week of October 4th. Landscaping and cleanup will be completed after the paving operation and all work to be completed by October 16th.