CITY, N.D. (NewsDakota.com) – The Valley City parking lot improvement project continues, crews finished most of the work in three parking lots including the City Hall parking lot, the city lot north of Our Savior’s Lutheran Church and the city parking lot south of the VFW Club. These parking lots are now open to the public.
A KLJ spokesperson said on Friday August 18th, construction will start on the parking lot north of the post office and the parking lot west of the Viking Room building in Valley City.
Then on Monday August 21st, construction will start on the Rosebud Visitor Center parking lot. This lot is being reconstructed into a concrete lot. A temporary parking lot will be designated to the west of the outdoor railroad exhibit near the Rosebud Visitor’s Center.
All of these parking lots will be closed while concrete work and the mill and overlay work is being completed.
Updated maps for all parking lot closures will be posted on the City of Valley City’s website (http://www.valleycity.us/) when they are taking affect. If you have any questions regarding the project please contact the KLJ office in Valley City at 845-4980.
Meanwhile, the Valley City Public Works Office drop box behind the post office will be closed starting Thursday August 17th for approximately 3 weeks due to the parking lot repair work.
Valley City resident are being asked to use the drop box in the Public Works entry or in the office between 7:30am to 5:00pm Monday-Friday until the parking lot project is completed.