N.D. (NewsDakota.com) – The Two Rivers Activity Center enters 2017 with the hope of being finished and opened by September.

Facilities Manager Amy Walters reports that since construction began, crews have lost a total of 19 days worth of work on the project. She pointed out that this includes the heavy snowfall, freezing temperatures and rains over the course of construction.

Walters says the project averages around 60 workers per day on site. She says with the recent weather, crews have been able to finishing roofing the facility.

One of the most often questions asked is “What is the latest progress with the construction?” Walters stated that they have provided a live-feed of the project that anyone can view at any time. She says now that most of the outside work is finished, they’ll move the camera inside so everyone can watch construction inside in real time.

You can click here to view the live camera feed. You can also find more information at jamestownparksandrec.com.