N.D. (NewsDakota.com) – The .6 million Two Rivers Activity Center is coming along nicely.

During an October 26th meeting, members of McGough, Jamestown Parks & Rec, & Zerr Berg Architects were updated on the latest construction. As of October 26th, there were 13 total days lost due to weather conditions. So far, concrete has been poured for a majority of available slabs, roofers finished the lesson pool roof, framing of the gym parapet and interior walls, and block layers were working on the fireplace.

The team will be reviewing plans to verify locations and the number of AED devices that are needed. A panic button will potentially be installed and a projector for the group fitness room is being looked at.

No injuries have been reported since construction began. The next update meeting will be held November 2nd at 1 PM.

Full information from the October 26th meeting can be found here.

October 31st Construction Update of the Two Rivers Activity Center
October 31st Construction Update of the Two Rivers Activity Center